Setting Up a Factory in Saudi Arabia as a Foreign Investor in 2026: From the MODON Contract to the Production-Stage Industrial License, Step by Step
Published:
Reviewed by the Investor Journey legal team · Last updated:
Planning to build a factory in the Kingdom? Drawing on the investor journeys published by the Saudi Authority for Industrial Cities and Technology Zones (MODON), the service pages of the Ministry of Industry and Mineral Resources and the National Center for Environmental Compliance, this guide sets out the order of steps from investment registration with MISA to upgrading the industrial license to production, the documents, the published timelines and fees, where judgment and risk lie, and the cost of common mistakes.
Last reviewed: 20 November 2026. This guide is based on MODON's published "Investor Journey for Industrial Lands" and "Investor Journey for Ready-built Factories" pages, its service pages, its Service Level Agreement and its "Cost of Industry" page; the service pages of the Ministry of Industry and Mineral Resources (MIM) on the Senaei platform; the e-services pages of the National Center for Environmental Compliance (NCEC); the Salamah portal page on the Civil Defense website; the Guidance on Technical Requirements for Food and Water Manufacture issued by the Saudi Food and Drug Authority (SFDA); and the Terms and Conditions published by the Ministry of Investment (MISA) (8th edition, 2026). Where we give practical recommendations, we mark them in the text with "we recommend" or "in our assessment". This is general information and does not constitute legal or technical advice on your particular situation. Procedures and fees are subject to change, so please consult the official source before applying. The decision on every application rests with the competent government authority alone.
The one-minute summary
- The official route is published: MODON's website sets out the investor journey for industrial land in three stages: contracting, building, then operation and production. For a foreign investor it begins with an investment registration request on the Invest Saudi platform, then the commercial registration (CR), then the industrial license under establishment on the Senaei platform, and then the contracting request on the Shareek platform.
- The industrial license has three stages: establishment, construction, and production. Under MIM's service pages, the license at the establishment and construction stages does not authorize the holder to start production.
- The industrial product request includes a personal interview: among the steps of its industrial allocation service, MODON lists scheduling applications for interview and conducting the personal interview, and it requires a valid CR, an investment license for a foreign investor, and an industrial license at the establishment stage.
- Plans go through a MODON-qualified consultant: the master plan and the safety plan are approved through the Shareek platform, on condition that a consultant qualified with MODON is engaged and the plans comply with the Saudi Building Code.
- Two environmental permits: a construction permit before the license is upgraded to the construction stage, and an operating permit before production. The studies are prepared by a service provider licensed by NCEC.
- Customs exemption follows the license stage: upgrading the license to construction enables the customs exemption for machinery and spare parts, and the raw materials exemption is granted at the construction stage for trial production in specified quantities, then for the full licensed quantities at the production stage.
- The production upgrade is the last stop: for it, MIM requires an operating license from the authority supervising the site, an operating environmental permit, licenses for restricted activities such as an SFDA license where applicable, and an energy allocation license.
1. Three decisions before any application
Before opening any platform, we recommend settling three decisions, because every later step is built on them:
- Where will the factory be located? In an industrial city supervised by MODON, or within the remit of another supervising authority such as the Royal Commission for Jubail and Yanbu, King Abdullah Economic City, or the area of the Ministry of Municipalities and Housing. At the production stage MIM requires a valid operating license from the authority supervising the site and lists these authorities as examples, and the safety and operating route differs between them. This guide mainly explains the route in MODON's industrial cities. For those considering zones with special incentives, we explained their rules in our guide to special economic zones.
- Industrial land on which you build, or a ready-built factory? MODON offers ready-built factories that it has fully constructed, in sizes of 350, 700 and 1,500 square meters, provided the intended activity is not on the list of activities prohibited in ready-built factories. The ready-built route is shorter, as section 4 explains.
- Is your activity restricted by another authority's license? At the production upgrade MIM requires licenses for restricted activities from the competent authorities, citing the SFDA and the General Authority for Military Industries as examples. A food or water factory therefore follows an additional SFDA route, set out in section 7.
If your company is not yet established, the route begins with registering the investment with MISA and entering the company in the commercial register. We explained this in our company formation guide for foreign investors, and how registration replaced the former license in our guide to registration with the Ministry of Investment.
2. Map of authorities and platforms
Authority — Role in a factory project — Platform
Ministry of Investment (MISA) — Registration of the foreign investment — Invest Saudi platform
Saudi Business Center — Commercial registration — Saudi Business Center platform
Ministry of Industry and Mineral Resources (MIM) — The industrial license and its stages; industrial customs exemptions — Senaei platform
Saudi Authority for Industrial Cities and Technology Zones (MODON) — Allocation and contracting, plan approval, building permit, electricity connection, building completion certificate and operating licenses inside industrial cities — Shareek platform
National Center for Environmental Compliance (NCEC) — Environmental permit for construction, then for operation — Environmental Permits and Licenses platform
Ministry of Energy — Energy allocation certificate — Ministry services
Saudi Food and Drug Authority (SFDA) — License to practice the activity for food factories and similar — SFDA services
Civil Defense — Safety license for sites within the remit of the Ministry of Municipalities and Housing — Salamah portal
A MISA condition that is often overlooked: the Terms and Conditions published on MISA's website (8th edition, 2026) state that establishments registered under industrial activities shall obtain the industrial license from the Ministry of Industry and environmental approval from the National Center for Environmental Compliance, and that the applicant shall complete all post-registration procedures within six months of the registration approval, including obtaining the licenses and approvals required to conduct the activities. We therefore recommend preparing the industrial project timeline before registration, not after it.
3. The steps in order for industrial land
We follow the order of MODON's "Investor Journey for Industrial Lands" (page last updated 13/10/2026) and add to each step what the competent authority has published about it.
Stage one: contracting
Step 1: Investment registration and commercial registration
MODON's journey for a foreign investor begins with two steps outside MODON: an investment registration request (foreign) on the Invest Saudi platform, then a commercial registration request on the Saudi Business Center platform. We recommend that the registration and the CR include the industrial activity you will license, because several MODON services require the activity registered in the CR to suit the nature of the request.
A note on terminology: MODON's service pages still list "an investment license if the investment is foreign" among the requirements. In practice today this refers to the registration document issued by MISA since the new Investment Law took effect. If the old name is requested, the document to submit is the one MISA issues today.
Step 2: Industrial license under establishment (Senaei platform)
MIM describes the industrial license as a document the ministry issues to the industrial investor to enable completion of the project's requirements, and its service page states that it is valid for one year only and does not authorize the holder to start production, with a processing time of 30 to 90 days. The application is filed online on the Senaei platform.
The importance of this step is that MODON requires an industrial license at the establishment stage for its industrial allocation service. In other words, the official order is: the license first, then the land request. The Senaei platform also offers a tool to search the available spatial presence for an industrial activity by activity name or code, and we recommend consulting it before choosing a city.
In practice: we recommend listing all the products you intend to manufacture and an accurate description of raw materials and machinery, because later customs exemptions depend on a valid industrial license, and the raw materials exemption is tied to the licensed quantities. Our team handles this stage, for those who wish, as part of our industrial license Saudi Arabia service.
Step 3: Registering on Shareek and the industrial product request
MODON launched the Shareek platform to unify its electronic systems, and contracting, allocation, contract amendment and monthly construction progress tracking requests are filed through it. MODON describes its industrial allocation service as enabling investors to apply for industrial products electronically and fully automated, and requires:
- A valid commercial registration.
- An investment license (MISA registration) if the investment is foreign.
- An industrial license at the establishment stage.
Its published steps: filing the application, review, scheduling applications for interview and conducting the personal interview, initial allocation with an indicative recommendation of the proposed site, pricing, submission of the recommendation, and approval. The completion time for an "industrial product request" in MODON's Service Level Agreement is 15 working days, which, according to the SLA, excludes time when the request is pending with the customer to complete deficiencies and time that depends on third parties.
For those who would like us to handle this, we offer a MODON registration service and a MODON industrial land request service in the city you choose, with the allocation decision remaining with MODON alone.
Step 4: The personal interview
The interview is a step stated in the allocation service, but MODON does not publish its topics or evaluation criteria on the service page. This is a point of genuine judgment:
- In our assessment, the interview should be treated as a test of the project's seriousness and clarity, not a formality; initial allocation and the site recommendation come directly after it in the service sequence.
- We recommend that it be attended by someone able to answer on the project's technical and financial aspects: products, production lines, the space requested and its justification, the investment cost and its funding, the timeline to production, and the workforce.
- We recommend preparing a project timeline and a brief feasibility study beforehand, consistent with the industrial license and the allocation request. An inconsistency between the space requested and the stated production volume, or between the products in the license and those described at the interview, weakens the application.
For those who wish, we offer MODON interview preparation: a project timeline, a brief feasibility study and preparation for the questions. Preparation does not mean influencing the outcome, which is MODON's decision alone.
Step 5: Environmental disclosure at the allocation stage
MODON publishes an environmental disclosure form evaluation service, whose purpose is to determine the factory's risk level in order to identify the environmental obligations of its activity and to evaluate the allocation request environmentally. The investor receives the appropriate disclosure form according to the facility's risk classification (an EIR or EP1 form), whose data is then reviewed and approved. Environmental assessment therefore begins before the contract is signed, not after.
Step 6: Signing the contract with MODON
Once the recommendation is approved, the contract is signed. Two points deserve attention:
- The financial consideration: MODON's "Cost of Industry" page publishes, for each industrial city, an annual fee per square meter and an allocation fee collected monthly or once depending on the city. The page states that the monthly allocation fee runs for twenty-four months and stops when production begins, and that its purpose is to motivate the investor to reach commercial production faster. Every month of delay before production therefore has a direct cost in cities where this fee is collected monthly.
- Timelines in the contract: we did not find in the published official sources a single general deadline for submitting plans or starting construction after signing. However, the building permit service requires an undertaking to comply with the timeline, signed by the owner and certified by the Chamber of Commerce, and MODON has a monthly construction progress tracking service. We therefore recommend reading the contract's clauses on timelines and penalties before signing, and having them reviewed legally.
Step 7: Plan approval (master plan and safety plan)
In MODON's journey this step falls within the contracting stage, directly after signing, through the Shareek platform. Its published conditions include:
- The contract status on Shareek must be open.
- A consultant qualified with MODON must be engaged, according to the type and sector of qualification, to prepare the plans.
- Plans are approved in accordance with the Saudi Building Code and MODON's approved building guides and requirements, and MODON's approved safety requirements for industrial safety designs.
- The consultant must attach the self-check list and a declaration of compliance.
- Documents include a land handover record approved by one of MODON's approved surveying offices.
- Payment of the approval fee.
MODON's published requirements for establishing factories state that the front setback on the road shall not be less than 13.5 m, and the side and rear setbacks not less than 6 m, and that the raw materials warehouse and the products warehouse are each sized to cover the factory's needs at 30% to 40% of the building area, together with worker services, safety and internal roads.
The completion time for a "request for plan approval" in the SLA is 5 working days. For those who wish, our MODON approved engineering office service connects you with a qualified partner office and follows the approval. Section 9 explains why we regard choosing the office before signing the contract as a decisive step.
Stage two: building
Step 8: Environmental permit for construction
It is requested on NCEC's Environmental Permits and Licenses platform and varies by activity category (detailed in section 5). Common to all categories is that the environmental plan or study is prepared by a service provider licensed by NCEC, with an undertaking to implement its findings and recommendations. The construction environmental permit is one of the documents for upgrading the industrial license to construction. For those who wish, we offer an environmental permit Saudi Arabia service in coordination with a licensed service provider.
Step 9: Energy allocation certificate
It is requested from the Ministry of Energy. In MODON's journey for industrial land it is a separate step in the building stage, and MIM lists an energy allocation license among the documents for the production upgrade. We recommend applying early if the factory depends on gas or feedstock, because the design of the production lines may depend on it.
Step 10: Upgrading the industrial license to construction
MIM describes this service as converting the project's status to construction after the establishment stage is complete and the requirements are met, with the license valid for one year and not authorizing production, and enabling the customs exemption for machinery and spare parts and partial labor endorsement. Its published documents:
- A valid industrial license.
- A valid spatial license or contract for establishing the factory (here, the contract with MODON).
- An environmental permit for construction.
Its published processing time is 30 days. MIM also publishes a renewal service for the construction-stage license that extends its validity for up to five years once all requirements are met. This stage is what is known in practice as the "construction industrial license".
Step 11: Building permit and construction
The building permit is requested through Shareek, and the SLA completion time for a "request for new building permit" is one working day. Its published documents and conditions include:
- An approved master plan, a project timeline, and a copy of the contract.
- An undertaking to comply with the timeline, signed by the owner and certified by the Chamber of Commerce.
- A contract with a qualified engineering consultancy to supervise construction and submit monthly reports.
- Selection of an engineering office and a contractor accredited by the Saudi Contractors Authority.
- A soil test, the approved architectural and safety plans, the project budget, and the permits of the relevant authorities.
For those who need a contractor, we offer industrial contractor matching, and in every case we recommend verifying the contractor's accreditation with the Saudi Contractors Authority before contracting.
Step 12: Customs exemption for machinery, equipment and spare parts
MIM publishes a "Customs Exemption for Equipment and Spare Parts" service that enables the industrial investor to obtain a customs exemption for machinery, equipment and spare parts after obtaining the industrial license. Its conditions: a valid CR, an industrial license that is valid and active, and no pending license cancellation or duplicate request. Its published processing time is 48 hours, and it is available at the construction and production stages.
In practice: we recommend not shipping machinery until the license has been upgraded to construction and the exemption has been issued, because a shipment arriving earlier may mean paying customs duty on it. For those who wish, we offer a customs duty exemption Saudi Arabia service for machinery and raw materials.
Step 13: Electricity connection
It is requested through Shareek, and its SLA completion time is 40 working days, the longest published time in the table. We therefore recommend placing it early in the timeline, not after the building is complete.
Step 14: Operating environmental permit
It is requested on the Environmental Permits and Licenses platform before operation, and rests on an updated environmental management plan for operation for category one, or an environmental audit study for categories two and three, prepared by a service provider licensed by NCEC. It is one of the documents for the production upgrade.
Stage three: operation and production
Step 15: Building completion and occupancy certificate and operating licenses
It is requested from MODON through Shareek, and its SLA completion time is 5 working days. The service page states that the building completion certificate is an operating license and is granted before the production stage begins for new partners. Its conditions include fire protection systems working properly and safety staff qualified and trained, and no hazardous observations such as unsafe storage of chemicals or flammable materials. On renewal, the operating license is valid for 6 months, one year or 3 years depending on the level of compliance with safety requirements.
Step 16: Licenses for restricted activities
If the activity is restricted by another authority's license, such as the SFDA's, that license is one of the documents for the production upgrade. Section 7 sets out the SFDA route.
Step 17: Upgrading the industrial license to production
MIM describes the service as converting the project's status to producing once the requirements are met and production begins. Its published documents:
- A valid industrial license.
- A valid operating license from the authority supervising the site (such as MODON, the Royal Commission for Jubail and Yanbu, King Abdullah Economic City, or the Ministry of Municipalities and Housing).
- An operating environmental permit.
- Licenses for restricted activities from the competent authorities where applicable.
- An energy allocation license from the Ministry of Energy.
- A Civil Defense certificate for sites within the remit of the Ministry of Municipalities and Housing.
Its published processing time is 30 days. This stage is what is known in practice as the "operational" or "final" industrial license. For those who wish, we handle it in our operational industrial license Saudi Arabia service.
Step 18: Raw materials exemption
MIM publishes a "Customs Exemption for Raw Materials and Trial Production" service for establishments holding an industrial license. It grants, at the construction stage, an exemption for raw materials for trial production in specified quantities, and the full licensed quantities at the production stage, subject to conditions including a valid CR and a valid, active industrial license, with a published processing time of 48 hours. MIM also has a separate service for an additional exemption that increases the exempted quantity within the licensed limit or adds licensed materials not previously exempted. The ceiling of the exemption is therefore what the license states, which is why step 2 stressed accurate data from the outset.
4. Ready-built factories: what is different?
MODON publishes a separate journey for ready-built factories (page last updated 4/11/2026). It is essentially the same route with a shorter building stage:
- Contracting stage unchanged: investment registration, CR, industrial license under establishment, contract request, contract signing, and plan approval request (master plan and safety plan).
- Preparation stage: the construction environmental permit, then the upgrade of the license to construction. The journey does not list the building permit, the electricity connection or the energy allocation certificate among its steps, and the building permit service exempts ready-built factories from some of its documents.
- Operation and production stage: the operating environmental permit, the building completion and occupancy certificate and operating licenses, then the production upgrade.
MODON also has an advance reservation service for units it builds, which requires a valid CR and an investment license for a foreign investor, includes a personal interview among its steps, and hands over the unit once it is structurally complete.
When is a ready-built factory the better fit? In our assessment: when the production lines can be installed in the standard sizes (350, 700 or 1,500 square meters) without material structural changes, and when shortening the time to production is the priority. If the industrial process requires special heights, loads or utilities, land may be the more accurate choice despite its longer route. Rental values for ready-built factories in each city are published on the "Cost of Industry" page.
5. Environmental permits in detail
NCEC classifies permits into three categories by environmental impact, each with a construction permit and an operating permit. NCEC also has an activity classification service (fee SAR 500, 10 working days) for those who do not know their activity's category. These are the service details as NCEC publishes them in its e-services directory:
Service — Technical basis required — Published time — Published fee
Construction permit, category one (low impact) — Environmental management plan from a licensed provider, an environmental rehabilitation plan where the regulations require one, and an undertaking — 10 working days — SAR 1,000
Construction permit, category two (medium impact) — Category-two environmental impact assessment from a licensed provider, and an undertaking — 30 working days — SAR 10,000
Construction permit, category three — Scoping report for the environmental impact assessment, then the assessment after the scoping report is approved, and an undertaking — 60 working days — SAR 13,000 to 275,000 depending on capital
Operating permit, category one — Updated environmental management plan for operation, and an undertaking — 10 working days — None
Operating permit, category two — Environmental audit study from a licensed provider, and an undertaking — 30 working days — None
Operating permit, category three — Environmental audit study from a licensed provider, and an undertaking — 30 working days — None
Two cautions: first, the fees above are NCEC's fees only and do not include the fees of the environmental service provider who prepares the study. Second, for every service NCEC reserves the right to request "any other requirements the Center deems necessary", so the published list is a minimum, not an exhaustive one.
6. Civil Defense and safety
The safety route differs with the factory's location, and this is a common source of confusion:
- Inside MODON's industrial cities: in MODON's journey, safety passes through safety plan approval together with the master plan, then the operating license and building completion certificate, which require working fire protection systems and qualified safety staff. MODON also offers an evacuation drill permit service and a chemicals disclosure service. MIM lists a Civil Defense certificate among the production-upgrade documents only for sites within the remit of the Ministry of Municipalities and Housing.
- Outside industrial cities, within the remit of the Ministry of Municipalities and Housing: a safety license is requested from Civil Defense through the Salamah portal. According to the service page, it is available to establishments with a valid CR, and its steps are: registering in the service as a license applicant, completing the fields after selecting the activity type, attaching the documents specified for the activity, paying the invoice, then awaiting the officer's approval and printing the license. For those who wish, we offer a civil defense license Saudi Arabia service.
In both cases we recommend designing the fire protection and alarm systems into the plan from the start, in line with the competent authority's requirements, because altering a building after construction costs far more than altering a drawing.
7. The SFDA: when does it come in?
If the factory produces food, bottled water or other products under SFDA oversight, the SFDA's Guidance on Technical Requirements for Food and Water Manufacture sets out the journey to obtain a license to practice the activity for factories within an industrial, economic or royal city in this order: approval of the location by the city authority, then industrial approval from MIM, then establishment of the factory, then an operation license from the city authority, then the final industrial license from MIM, and then issuance of the license to practice the activity by the SFDA.
Among the requirements in the same guidance: the factory's areas must be proportional to the factory construction plan approved by the SFDA, and changing the factory area by increase or decrease is strictly prohibited without SFDA approval. In practice, the plan of a food factory should therefore be designed from the start to SFDA requirements, not to MODON's requirements alone. For those who wish, we offer SFDA plan approval and an SFDA factory license service.
What about ISO certificates? They are not among MIM's published documents for the production upgrade, but buyers and supply chains often ask for them. For those who wish to prepare for them after start-up, we offer an ISO certification Saudi Arabia readiness service; the certificate itself is issued by an accredited certification body.
8. Published costs and what is not published
What the authorities have officially published (as of the review date):
- MODON: tables of annual fees and allocation fees for each industrial city, rental values of ready-built factories in their three sizes, and water, electricity and gas prices, on the "Cost of Industry" page. Published service prices include master plan approval at SAR 1 per square meter, with a minimum of SAR 5,000 and a maximum of SAR 25,000, and safety plan approval at SAR 5,000.
- NCEC: the construction permit fees in the table above, with no fee for operating permits according to its pages.
- Civil Defense: the Salamah portal page states a service cost of 0, while listing "pay the invoice" among the steps, so we leave what is payable to what appears on application.
What we did not find published, and have therefore not stated: fees for issuing and upgrading the industrial license, fees of engineering offices, consultants and environmental service providers, and the cost of construction and fit-out. We recommend that no investment decision be built on an estimate of these items before actual quotations are obtained.
9. Where do judgment and risk lie?
The steps above are published, and someone with the time can follow them alone. But there are points the texts do not answer, and most of the difficulties we see arise there:
- The order of contracts: the official route places plan approval directly after signing the MODON contract. Whoever signs the contract and only then starts looking for a qualified consultant begins the financial commitment before the engineering work begins. In our assessment, the qualified engineering office should be chosen, and its scope and timeline agreed, before signing.
- The interview: MODON does not publish its evaluation criteria, so preparing for it is a matter of professional judgment, not a guaranteed formula. Our yardstick is consistency: the interview should say what the license, the application and the study say.
- Environmental categorization: the difference between category two and category three is a difference in time (30 working days against 60), in fees (SAR 10,000 against up to SAR 275,000) and in the study required. The category depends on how the activity and processes are described, so we recommend requesting a formal classification when in doubt.
- A site outside industrial cities: it requires a valid spatial license or contract, suitability of the activity for the location, and a different safety route. It is a legitimate option, but harder to assess.
- MISA's six-month condition: six months to complete post-registration procedures, including the required licenses. A greenfield industrial project is unlikely to be complete within that time, so we recommend examining the effect of this condition on your file with MISA early.
10. Common mistakes and their cost
Mistake — Why it happens — Potential cost
Signing the MODON contract before agreeing with a qualified consultant — Assuming the plan is a distant later step — The contract's financial obligations run, including the monthly allocation fee in cities where it is collected monthly until production begins, without engineering progress
Signing a lease for a site outside industrial cities before confirming its suitability for the activity — Relying on the property's commercial classification rather than spatial approval — The construction upgrade cannot proceed, because MIM requires a valid spatial license or contract for establishing the factory
Attending the interview without someone who knows the technical and financial figures — Treating it as a formality — A weaker application or delayed allocation
An industrial license with incomplete products or materials — Rushing the establishment stage — A raw materials exemption ceiling below actual needs, and later amendment requests
Shipping machinery before the construction upgrade and the exemption — Not linking the purchasing schedule to the licensing schedule — Paying customs duty that could have been exempted
An environmental study by a provider not licensed by NCEC — Choosing the cheapest option — Rejection of the application and a repeated study
A contractor not accredited by the Saudi Contractors Authority — Not checking before contracting — A stalled building permit
A food factory plan that ignores SFDA requirements — Designing to MODON's requirements alone — Structural changes before the license to practice the activity
Starting production before the production upgrade — Assuming the construction license is enough — A clear violation, since the license before that stage does not authorize production
11. Our role and the legal boundaries
- Investor Journey is an independent private firm. It is not MODON, MIM, NCEC, Civil Defense or the SFDA, and is not affiliated with any of them. Allocation, licensing and permit decisions rest with each authority alone, and no intermediary can guarantee them.
- Technical work belongs to those legally qualified to do it: plans are prepared and signed by a consultant qualified with MODON, environmental studies by a service provider licensed by NCEC, and construction by an accredited contractor. Our role in this work is coordinating with qualified partners and following the procedures, not acting in their place.
- What our legal team provides: advice on the investment and entity structure, review of the MODON contract and its timeline and obligation clauses before signing, review of contracts with engineering offices and contractors, review of leases for sites outside industrial cities before they are signed, and follow-up of the file with the authorities.
- What Investor Journey provides: we can take on the whole journey under the supervision of our legal team, from advice through procedure to completion: setting the order of steps, preparing and filing the applications with the authorities, following them up to a decision, and coordinating with the qualified consultant, contractor and service providers, so that you can focus on what matters most in your project. Any of these tasks can also be requested as a standalone service.
- This guide is general information: it does not replace reading the contract and the conditions in force at the time of application, nor advice addressing the facts of your project.
From practical experience: the whole industrial journey in one hand
We do not know these procedures from the texts alone: the founder of Investor Journey set up a food factory personally, from registration with the Ministry of Investment and the commercial registration, through MODON and the industrial license, to the SFDA license and the operating license. From that experience we know where delays usually occur, and which steps are costly when taken too early or too late.
The recurring problem is that investors learn the procedures while carrying them out, and their file is split among several specialists, each handling one part while no one holds the overall sequence; what could have been completed in months then takes far longer, and mistakes and costs accumulate. This is why we offer the whole industrial journey as part of our company formation services: from investment registration and the commercial registration, to the licenses specific to the factory's field, such as the SFDA license in the food sector, through to the operating license, with correct procedures and a sequence that shortens time and cost as far as possible, under the supervision of our legal team. The decision on every allocation and license rests with the competent authority alone.
Each stage can also be requested as a standalone service:
- The industrial license in its three stages: the founding industrial license, then the construction industrial license, then the upgrade to the operating license.
- The environmental permit in its two stages: the construction environmental permit, then the operating environmental permit.
- The SFDA: factory plan approval and the factory license.
- Legal review of contracts before signing: the MODON contract, the engineering office or contractor contract, and the industrial site lease outside industrial cities.
Next step
A factory is a multi-authority project, and what costs most is usually not the authorities' fees but the order of steps: a contract signed too early, machinery arriving before its exemption, or a plan that must be redone. The Investor Journey team would be pleased to study the project with you before the first application and to propose the order best suited to it. We suggest starting with a consultation session on company formation and licensing, or requesting our service on how to open a factory in Saudi Arabia, which manages the full industrial project from registration to the production upgrade.
Frequently asked questions
Is an industrial license required before requesting land from MODON?
Yes. According to MODON's industrial allocation service page, the service requires a valid CR, an investment license for a foreign investor, and an industrial license at the establishment stage. MODON's published investor journey also places the industrial license under establishment before the contracting request. The advance reservation service for ready-built units does not list the industrial license among its published requirements.
What is the difference between the construction and the operational industrial license?
MIM divides the license into three stages: establishment, construction, and production. In practice, "construction license" refers to the construction stage, which requires a spatial contract and a construction environmental permit and enables the customs exemption for machinery, while "operational" or "final" license refers to the production stage. Before the production stage, the license does not authorize production.
Does the MODON application include a personal interview?
Yes. MODON lists scheduling applications for interview and conducting the personal interview among the steps of its industrial allocation service, and also in its advance reservation service for units. MODON does not publish its evaluation criteria, so we recommend that it be attended by someone familiar with the project's technical and financial aspects, with a project timeline and a brief feasibility study.
Who prepares the factory's engineering plans?
For plan approval, MODON requires engaging a consultant qualified with MODON according to the type and sector of qualification, and compliance with the Saudi Building Code and MODON's approved building and safety guides. The published master plan approval fee is SAR 1 per square meter, with a minimum of SAR 5,000 and a maximum of SAR 25,000, and safety plan approval is SAR 5,000.
When is the environmental permit required, and who prepares the study?
It is requested twice from NCEC: a construction permit before the industrial license is upgraded to construction, and an operating permit before the production upgrade. The environmental plan or study is prepared by a service provider licensed by NCEC, and the time and fees vary with the activity's category.
When can the customs exemption for machinery and raw materials be obtained?
According to MIM's pages, upgrading the license to construction enables the customs exemption for machinery and spare parts, and the exemption requires a valid CR and a valid, active industrial license. Raw materials are exempted at the construction stage for trial production in specified quantities, and at the production stage for the full licensed quantities.