The Wafi Off-Plan Sales License in Saudi Arabia: A Developer's Guide from Qualification to the Escrow Account, and the Route for Foreign Developers

Published:

Reviewed by the Investor Journey legal team · Last updated:

Do you intend to sell or lease units in your project before construction is complete in the Kingdom? Drawing on the Off-Plan Real Estate Projects Sale and Lease Law, its Implementing Regulations and the Wafi program pages of the Real Estate General Authority (REGA), this guide sets out the full licensing route: qualification in the developers' register, the marketing license, the project license, the escrow account and the roles of the engineering consultant, chartered accountant and bank, followed by the route for foreign developers and the structural options available, with their legal limits.

Last reviewed: 20 November 2026. This guide is based on the Off-Plan Real Estate Projects Sale and Lease Law issued by Royal Decree No. M/44 dated 10/3/1445H, its Implementing Regulations issued by decision of the Board of the Real Estate General Authority (REGA) in Shawwal 1445H (April 2024) as published on REGA's website, the Wafi program page on REGA's website, REGA's criteria for assessing the capabilities of a legal person for entry in the developers' register, the table of violations of the Law and its Regulations and their penalties, the Investor Guide published by the Ministry of Investment (MISA) (13th edition, 04-2026), and the Anti-Concealment Law. This is general information and does not constitute legal advice on your particular project. Procedures are subject to change, so please consult the official source before applying. The decision on every qualification or license application rests with REGA alone.

The one-minute summary

  • No off-plan sales without two stages: no developer may sell or lease off-plan unless entered in the developers' register, and a project may not be advertised or exhibited unless the project itself is licensed (Article 3 of the Law).
  • "Wafi" is the program's name: REGA provides its services on its electronic platform, from developer qualification to the project license application.
  • Qualification by points: a legal person needs a valid commercial registration (CR) and at least 35 of 100 points, and the points required rise with the project's size to 45 and then 55 (Articles 3 and 11 of the Regulations).
  • The marketing license is optional and restricted: it may be requested before the project license, REGA decides within 10 working days, it lasts no more than 180 days, no more than 5% of a unit's value may be received during it, and the amounts are deposited in the escrow account (Articles 8 and 10 of the Regulations).
  • The project license requires a complete file: a CR permitting real estate development, a building permit, a title deed, contracts with an engineering consultant and a chartered accountant, a feasibility study, an escrow account agreement with a licensed bank, and more. REGA decides within 30 days of the documents being complete (Article 6 of the Law).
  • The escrow account is the core of the system: a separate account for each project, disbursement by a document signed by the developer, the engineering consultant and the chartered accountant, and non-construction expenses capped at 20% of the value of units sold (Articles 9 to 12 of the Law).
  • The foreign developer: starts with investment registration at MISA and a CR with the real estate development activity, then qualification in the developers' register. The most delicate parts of the file are the points tied to a prior delivery record and local requirements such as Saudization and social insurance.
  • The heaviest penalty: selling off-plan or collecting money without a license, or failing to deposit it in the escrow account, is punishable by imprisonment of up to 5 years or a fine of up to SAR 10 million, or both (Article 24 of the Law).

1. What are off-plan sales, and when is a Wafi license required?

The Law defines a real estate project as one to be developed for the sale or lease of developed land or real estate units off-plan, before execution begins or during construction (Article 1). It applies to off-plan sale and lease in which money is received from buyers, tenants or financiers (Article 2).

Three rules follow from this:

  1. Qualification comes first: a developer not entered in the developers' register may not carry on the activity (Article 3).
  2. A license for each project: entry in the register is not enough; each project needs its own license, requested after entry (Article 6).
  3. No marketing before licensing: no advertising in local or foreign media and no exhibitions except for a licensed project (Article 3), which is why the marketing license introduced by the Regulations matters. We explain it in section 4.

A developer under the Law is a legal person licensed to own or lease real estate in order to develop and sell or lease it, and includes the main developer and a sub-developer acting under an agreement with the main developer (Article 1). REGA may, where needed, register a natural person under narrower rules and caps (Article 7 of the Law and Article 12 of the Regulations).

The license types shown on the Wafi program page are: off-plan sales license (default path), off-plan sales license (immediate path), marketing license with receipt of amounts, marketing license without receipt of amounts, lease license, scope license and real estate contribution license. The page does not state the conditions of the immediate path, so we recommend checking them on the platform before building a timetable on it.

2. The parties to the project and their roles

Party — Role under the Law — Reference

Developer — Entered in the developers' register, applies for the license, and is bound to execute, disclose and deposit amounts in the escrow account — Law, Articles 3, 6 and 20; Regulations, Article 14

Landowner (if not the developer) — Bound to the developer by agreement, and consents to the annotation of the deed against disposal — Law, Article 6(f); Regulations, Articles 11(4) and 19

Engineering consultant — An engineering office licensed by the Saudi Council of Engineers and approved by REGA for the project; certifies disbursement documents, submits progress reports and reports violations — Law, Articles 1, 11, 18 and 19; Regulations, Articles 6 and 33

Chartered accountant — Licensed by the Saudi Organization for Chartered and Professional Accountants; verifies deposits, monitors the 20% cap, prepares financial statements and holds the 5% retention — Law, Articles 12 to 15; Regulations, Articles 7 and 15

Bank — A bank licensed in the Kingdom that opens the escrow account under an agreement with set terms; its violations are reported to the Saudi Central Bank — Law, Articles 6(n) and 19; Regulations, Article 26

Real estate broker (if any) — Markets the project under the Real Estate Brokerage Law; REGA may ask for a copy of its agreement with the developer — Law, Article 5; Regulations, Article 9

Approval requirements for the engineering consultant and the chartered accountant

  • Engineering consultant (Article 6 of the Regulations): a valid CR, a license from the Saudi Council of Engineers, and passing of REGA's approved qualifying program by 10% of its engineers or five of them, whichever is fewer, with the project manager among those who have passed. If the project's value exceeds SAR 25 million, a Balady classification certificate for city service providers at the grade matching the project's value is required.
  • Chartered accountant (Article 7 of the Regulations): a valid CR, a license from the Saudi Organization for Chartered and Professional Accountants, and passing of REGA's approved qualifying program by 10% of the firm's accountants or four of them, whichever is fewer.

A practical note: choosing these two parties is not a formality. Their signatures are a condition of every disbursement from the escrow account, and they must report the developer's violations within 5 working days of learning of them (Article 33 of the Regulations). We therefore recommend that their contracts set out the scope of work, fees and replacement mechanism clearly, and follow the guidance templates prepared by REGA (Article 19(2) of the Regulations).

3. Stage one: qualification in the developers' register

Conditions of entry (Article 3 of the Regulations)

  • For a legal person: a valid CR and at least 35 of 100 points under the assessment table.
  • For a natural person (where needed): at least 35 of 55 points.
  • A developer may ask for its points to be raised if its capabilities change after entry.
  • Entry is suspended if the developer falls below the minimum, with three months to correct the position, after which it is struck off. Suspension or striking off does not affect projects already licensed.

Assessment criteria for a legal person (Article 5 of the Regulations, and the criteria document published on REGA's website)

Area — Criterion — Weight — Type

Financial — Financial statements from an approved chartered accountant (points range from 20 down to 5 according to the ratio of liabilities to assets) — 20 — Mandatory

Financial — Clean credit record certificate from a licensed company, dated no more than three months before the application — 10 — Mandatory

Technical — Statement of projects executed in the past 10 years (10 points per project) — 30 — Optional

Technical — Methodology followed in one of the executed projects — 10 — Optional

Institutional — Approved organisational structure — 1 — Mandatory

Institutional — Work regulations approved by the Ministry of Human Resources and Social Development — 3 — Mandatory

Institutional — Occupational health and safety regulations or ISO 45001 certificate — 3 — Mandatory

Institutional — Saudization certificate (Nitaqat band) — 2 — Mandatory

Institutional — Social insurance certificates and number of subscribers — 3 — Mandatory

Institutional — Passing of REGA's approved qualifying program by the owner, manager or an employee — 3 — Mandatory

Institutional — Valid certificate from the Zakat, Tax and Customs Authority — 5 — Mandatory

Institutional — Accredited engineers employed by the establishment — 5 — Optional

Institutional — Social responsibility programs — 5 — Optional

The project you wish to license sets the points required (Article 11(5) of the Regulations):

Project — Points required

Individual developer's project — 35 or more

Legal person's project with built-up area under 15,000 m² — 35 or more

Legal person's project with built-up area under 25,000 m² — 45 or more

Legal person's project with built-up area over 25,000 m² — 55 or more

A candid note: where does judgment come in at qualification?

Adding up the weights in the table, the mandatory criteria total 50 points and the optional criteria 50 points, of which 40 points depend on previously executed projects (the statement of projects and the methodology of one of them). In practice, this means:

  • A new entity with no delivery record may reach the minimum (35 points) if it meets the mandatory criteria with good scores, which is enough for projects under 15,000 m².
  • Larger projects (45 or 55 points) leave very little margin for an entity without a record, since reaching 55 points then depends on almost full marks on everything other than the delivery record.
  • We have found no official text stating whether projects executed outside the Kingdom, or in the name of the parent company, count towards the Saudi entity's points. We recommend confirming this with REGA before building the first project's plan on the assumption that they do.

Qualification steps

  1. Prepare the local documents first: work regulations, Saudization certificate, social insurance certificates, zakat certificate and organisational structure. Many of these are issued only once the establishment is operating and its employees are registered; we explain the Saudization requirements in our guide to Saudization, Nitaqat and Qiwa.
  2. Financial statements from a chartered accountant: an opening financial statement for a new establishment (under one year), or statements for one or two years depending on the establishment's age.
  3. A recent credit record certificate, dated no more than three months before the application.
  4. Passing of the qualifying program by the owner, the manager or an employee registered with social insurance.
  5. Register on the off-plan sales platform and file a "real estate developer qualification" application with the documents and data.
  6. Follow the assessment result, and ask later for the points to be raised if the establishment's capabilities improve.

4. Stage two (optional): the project marketing license

The Regulations allow a developer to request a project marketing license before the project license itself (Article 8(1)), which makes it possible to test demand before the file is complete.

  • Documents (Article 8(2)): the title deed number, the number of the marketing contract with the broker if any, a copy of the development contract with the landowner if any, and the architectural designs and engineering plans.
  • Decision period: 10 working days from completion of the application, and any rejection must state reasons (Article 8(3)).
  • Duration: no more than 180 days, extendable for one or more equal periods for projects that do not require receipt of reservation amounts (Article 8(4)).
  • If you wish to receive reservation amounts during the marketing license (Article 10): disclose the project's status and future plans, receive no more than 5% of the unit's value, and deposit all reservation amounts in the escrow account designated for this.
  • If the period ends without the project license being completed, REGA returns the deposited amounts to their owners (Article 10(2)).

The cost of a mistake here is set in figures: receiving a reservation above 5% is penalised in the violations table by a fine of 2% of the unit's value capped at SAR 50,000 for a first offence, 4% capped at SAR 100,000 for a second, and then striking off from the developers' register with no re-entry for up to one year for a third.

5. Stage three: the project license for sale or lease

Documents (Article 6 of the Law)

The registered developer files the license application with:

  1. A valid CR permitting the real estate development activity.
  2. A chamber of commerce membership certificate.
  3. A copy of the credit record from a company licensed for credit services.
  4. A valid building permit for the project.
  5. A valid title deed for the property to be developed.
  6. The agreement with the landowner or the holder of its usufruct.
  7. The agreement between the main developer and the sub-developer, if any.
  8. The approved architectural designs and engineering plans.
  9. The contract with the engineering consultant.
  10. The contract with the chartered accountant.
  11. An economic feasibility study from a consultancy office covering estimated costs, required expenditure, cash flow and expected execution period.
  12. An undertaking to begin construction within six months of the license date.
  13. A form of sale contract with the buyer, with delivery dates fixed to the day.
  14. An escrow account opening agreement with a bank licensed in the Kingdom.

REGA may add or amend some conditions.

What the Regulations add (Article 11)

  • The feasibility study also covers the estimated financial, construction and marketing data, expected financial and administrative expenses, unit delivery period and expected sources of finance.
  • A letter from the Developers' Services Center "Etmam", or any authority competent for building permits, confirming the project's conformity with building permit requirements, plans and designs, which replaces the building permit and designs.
  • The approved unit subdivision record if the project contains subdivided units.
  • A letter from the property owner consenting to the annotation of the deed against disposal until development is complete, except for properties registered in the real estate register.
  • Reaching the points required for the project's size, as in the table above.

The model sale contract

REGA prepares a model contract for sale and lease covering the payment schedule, the consequences of late payment by the buyer, compensation and market rent when the developer is late, including termination, the execution period and any extensions, and common ownership. The developer may amend it only with REGA's approval (Article 20 of the Regulations). The contract must include the parties' acknowledgement that REGA may substitute another developer if the project stalls (Article 20(3)). Using a contract other than the model, or amending it without approval, is a violation penalised in the table by a warning, then a fine of 5% of the unit's value capped at SAR 100,000, then striking off.

Steps

  1. Confirm the entry and points appropriate to the project's size.
  2. Conclude the core contracts: with the landowner if not the developer, with the engineering consultant, with the chartered accountant, and the escrow account agreement with the bank.
  3. Complete the building permit or conformity letter, the approved designs and the subdivision record if needed.
  4. Prepare the feasibility study with the data required by Article 11 of the Regulations.
  5. File a "real estate project license application" on the platform and choose the appropriate license type.
  6. Await the decision: REGA decides within 30 days of the documents being complete; if that period passes without a decision, the application is deemed approved, and a rejection must state reasons (Article 6 of the Law). We nonetheless recommend not starting sales until the license has actually been issued, since the date on which the documents were "complete" may itself be disputed.
  7. After issue: REGA requests the annotation of the deed against disposal until development is complete (Article 8 of the Law), and the escrow account is then activated (Article 9).

Dividing the project into scopes

REGA may divide a project into several scopes, provided that it approves the start of each scope and that each scope has its own escrow account and its own engineering and financial reports (Article 13 of the Regulations). This is a useful option for large projects, tying finance to phases rather than tying the whole project to a single account.

6. The escrow account: how does the money move?

The basic rules

  • A separate account in the name of each project, activated only after the license and the deed annotation (Article 9 of the Law).
  • Reserved for spending on the licensed project only, and not subject to attachment by the developer's creditors (Article 10(1)).
  • Finance is deposited in it: if the developer or landowner obtains finance for the project, it must be deposited in the escrow account (Article 10(2)).
  • Payments according to progress: according to the program page, payments are transferred to the escrow account according to the engineering completion percentage and the payment schedule in the contract.

What the bank agreement must contain (Article 26 of the Regulations)

A separate account with a unified number used as the deposit reference, in Saudi riyals, spending for the project only, by cheques or transfers only, a reference number for each deposit stating the unit number, no delegation of the bank's tasks to another party during execution, statements provided to REGA on request, no closure of the account without REGA's approval, and no ATM or credit cards issued on the account.

The role of the Saudi Central Bank: if REGA establishes that a bank has violated the Law or the Regulations, it must notify the Saudi Central Bank in writing (Article 19(3) of the Law).

Disbursement from the account

  • By a disbursement document submitted by the developer to the bank, certified by the engineering consultant and the chartered accountant, stating the amounts and their justification (Article 11 of the Law and Article 27 of the Regulations).
  • The cap on non-construction expenses: administrative, marketing and other expenses may not exceed 20% of the value of the unit sold, and the chartered accountant ensures that their total does not exceed 20% of the total value of units sold (Article 12 of the Law).
  • Disbursement at REGA's request in specified cases, including paying government dues, refunding buyers and transferring the balance to a substitute developer's escrow account (Article 28 of the Regulations).

A candid note: land price and finance fall within the 20% cap

The Regulations treat paying the land price to the owner and repaying finance as non-construction expenses (Article 29). This means that a developer who relies on buyers' money to pay for the land or finance instalments will find these confined within the same cap that covers marketing and administration. This is one of the points most often overlooked in feasibility studies, so we recommend building the project's finance structure around it from the outset.

Surplus and retention after completion

  • Withdrawing the surplus: the developer may, with REGA's approval, withdraw any amount exceeding the actual total cost of completing the project, based on a report from the contractor and the engineering consultant, with the chartered accountant keeping 20% in the account until the project ends (Article 13 of the Law and Article 30 of the Regulations).
  • 5% retention after the completion certificate: the chartered accountant retains 5% of the total construction cost, or the developer provides a bank guarantee for the same percentage, released only one year after the project ends, or on provision of a latent defects insurance policy (Article 14 of the Law) approved by the Insurance Authority and running for at least one year (Article 31(4) of the Regulations).

7. After licensing: execution, reporting and delivery

  • Start of works within 6 months: otherwise REGA may strike the developer off the register absent an acceptable excuse (Article 25 of the Law). In the violations table: a warning, then a fine of 2% of the project's value capped at SAR 500,000, then striking off.
  • Periodic reports: REGA may request a progress report monthly if the built-up area exceeds 5,000 m² or the number of units exceeds 30, or the project is governmental or in a government development area, and every three months otherwise (Article 25 of the Regulations).
  • The public database: the developer adds the names of the contractors, engineering consultant and chartered accountant, reports, completion certificates, plan amendment records and supplier data (Article 23 of the Regulations), and REGA makes part of it public, including the developer's name and classification and a survey of buyers' views (Article 24).
  • Amending the executive plans: permitted only with the approval of REGA and of the buyers or tenants (Article 32 of the Regulations).
  • The buyer's right of access: the developer allows each buyer to view the accounting record for their unit and provides a copy within 10 working days (Article 22 of the Regulations).
  • Delay and default: REGA may grant an additional period of no more than one year; the developer is in default if the project is not completed after it, or if works stop for more than 180 days, unless the developer gives a legitimate reason accepted by REGA (Article 34 of the Regulations).
  • Compensation for delay: for developed land, not less than 2% per year of the sale value; for a unit, not less than the market rent set by an accredited valuer (Article 35 of the Regulations).
  • Warranties after delivery: according to the frequently asked questions on the program page, the warranty for structural works (foundations, concrete and insulation) is ten years, and for mechanical and electrical installations one year, from the date the unit is delivered.
  • At the end of the project: the developer submits financial statements prepared by the chartered accountant (Article 15 of the Law) and gives buyers the as-built plans (Article 14 of the Regulations).

8. The foreign developer: the full route, step by step

The rule the route is built on

The Law states no nationality requirement for the developer, but requires a legal person licensed to carry on the activity, whose CR permits real estate development (Articles 1 and 6(a)). The foreign investor's route is therefore a Saudi entity registered with MISA, followed by qualification and licensing like any other developer. We have not found real estate development among the special registration categories in the Investor Guide (13th edition) that carry a minimum capital or a Saudi participation percentage; the final reference is what MISA's platform shows when the activity is selected.

Steps

Step 1: Choose the entity. Usually a limited liability company or a simplified joint stock company; the entity may be a joint venture with a Saudi partner if the project structure calls for it. We explain the differences in our guide to choosing between an LLC and a simplified joint stock company.

Step 2: Register the investment with MISA with the real estate development activity. We explain the requirements in our guide to the foreign investment license, and for those who would like us to handle it, we offer the Investment License service.

Step 3: Articles of association and CR with the real estate development activity, then chamber of commerce membership, the bank account and tax registration. For the full route, please see our company formation guide for foreign investors or request the Complete Company Formation Bundle. To prepare the developing entity and its licensing requirements in full, we offer a real estate developer license service for foreign investors.

Step 4: Local operations before qualification. Register employees with social insurance, obtain the Saudization certificate, have the work regulations approved, adopt occupational health and safety regulations and an organisational structure, obtain the zakat certificate, and have one of the officers pass the qualifying program. All of these are mandatory criteria in the points table. If the investor will manage the company personally from within the Kingdom, we explain this in our guide to the General Manager visa.

Step 5: Financial statements and credit record. An opening financial statement from a chartered accountant for a new establishment, and a clean credit record certificate from a licensed company.

Step 6: Apply for qualification in the developers' register, with a realistic estimate of the points in light of the candid note in section 3.

Step 7: Secure the land. Either own it in the company's name under the Law of Real Estate Ownership by Non-Saudis, whose rules and geographic scopes we explain in our guide to foreign real estate ownership, or enter into a development agreement with the landowner (section 9).

Step 8: The marketing license if you wish to have one, then the project license and the escrow account, as in sections 4 and 5. For those who would like us to prepare and follow this file until the decision, our Wafi license Saudi Arabia service covers the readiness review, preparation of the application and follow-up.

A candid note: owning land outside the geographic scope

The Law of Real Estate Ownership by Non-Saudis governs ownership by a Saudi company with a foreign shareholder inside and outside the geographic scope; outside the scope, ownership is for specified purposes and requires MISA's prior approval. We have found no express official text stating whether buying land in order to develop it and sell its units counts as "carrying on the activity" for that purpose. If the project land lies outside the scope, this question should be studied before any financial commitment.

9. Structural options and their legal limits

1. A development agreement with the landowner

Instead of buying the land, the developer may be a non-owner, provided there is an agreement between it and the landowner or the holder of its usufruct (Article 6(f) of the Law). REGA prepares a guidance template for it, setting out the developer's and owner's responsibilities and obligations towards the buyer (Article 19(1) of the Regulations). The owner consents to the annotation of the deed against disposal until development is complete.

  • Its advantage: it reduces the capital required and avoids the questions of ownership outside the scope.
  • Its limit: paying the land price to the owner from the escrow account is a non-construction expense within the 20% cap (Article 29 of the Regulations), and the split of returns should be built around this.
  • What it should contain: each party's share and how it is calculated, each party's responsibility towards buyers, the mechanism for dealing with default, and what happens if a substitute developer is appointed. For drafting and reviewing this agreement, we offer Contract Drafting & Review.

2. The sub-developer

The Law defines a sub-developer as a licensed legal person acting under an agreement with the main developer (Article 1), and their agreement is filed with the license application (Article 6(g)). This is a route for a foreign developer to enter the market through an existing developer's project, provided that it is itself licensed, rather than working in someone else's name.

3. A joint venture with a Saudi developer

A joint venture company between the foreign investor and a Saudi developer may combine local experience and capital. A candid note: points in the developers' register are counted for the applying entity, and we have found no text allowing a partner's delivery record to count towards the new company's points, so we recommend confirming this with REGA before building the partnership on that assumption. For drafting the partners' rights, decisions and exit mechanism, we offer Articles of Association with Governance Clauses.

4. Dividing the project into scopes

This allows a start with a smaller scope matching the entity's available points and financial capacity, with a separate escrow account for each scope (Article 13 of the Regulations), although how the required points are assessed for each scope is a question we recommend confirming with REGA.

The dividing line: when does an arrangement become concealment?

Concealment (tasattur) under the law is an agreement or arrangement through which a person enables a non-Saudi to carry on an economic activity for which they are not licensed, using the concealer's license or approval (Anti-Concealment Law, Article 2). In the off-plan sector, the warning signs we recommend avoiding are:

  • A project licensed in a Saudi developer's name but managed, financed and collected by an unregistered foreign investor, with a side agreement giving the Saudi developer a fixed sum for its name.
  • Unrestricted powers of attorney or banking mandates that make a non-Saudi the controller of the establishment otherwise than as the articles of association provide.
  • A nominal development agreement in which the "owner" is a front for an unlicensed investor.

A lawful arrangement is: a foreign investment openly registered with MISA, a developing entity qualified in its own name, genuine agreements with genuine responsibilities, and buyers' money in the escrow account alone. Concealment penalties reach five years' imprisonment and/or a fine of SAR 5 million (Article 9), together with dissolution of the establishment, cancellation of the license and deportation of the non-Saudi (Articles 11 and 12). A single arrangement may also amount to the offence of submitting incorrect documents or data for a license application under Article 24 of the off-plan Law.

10. Penalties and the cost of mistakes

Offences (Article 24 of the Law)

The following are punishable by imprisonment of no more than five years or a fine of no more than SAR 10 million, or both, without prejudice to any heavier penalty:

  • Anyone who sells or leases off-plan, or collects money from buyers or tenants, without a license.
  • Anyone who submits incorrect documents or data for a license application.
  • Anyone who knowingly offers or advertises fictitious projects.
  • Anyone who embezzles, squanders or wrongfully uses money handed over for the project.
  • Anyone who receives money to reserve land or units with the intention of selling them off-plan and does not deposit it in the escrow account.
  • A chartered accountant who deliberately issues an incorrect report, and a consultant who knowingly certifies incorrect documents.

The Public Prosecution investigates and prosecutes before the competent court, and the court may order a summary of the judgment published at the offender's expense (Article 26).

Administrative violations

  • Fines of up to SAR 1 million imposed by the violations committee, with objection before the Administrative Court within 60 days of notification (Article 21 of the Law).
  • Striking off the developers' register for failing to start works within 6 months without excuse, repeated delay or default, or poor quality, and mandatorily on bankruptcy or a penalty for a grave violation (Article 25).
  • The violations table sets the penalty by repetition; examples include those mentioned above: reservations above 5%, a non-model contract and late start of works. Another example is amending the executive plans without REGA's approval: a fine of 2% of the project's value capped at SAR 300,000, then 4% capped at SAR 500,000, then striking off with no re-entry for up to three years. The penalty decision sets a period to correct the violation of no less than 10 days and no more than 180 days.

The real cost exceeds the fine: striking off stops the developer from taking on new projects, the developer's classification is public in the database, and in case of default REGA may substitute another developer and transfer the escrow balance to it (Articles 20(3) and 28(4) of the Regulations).

Common mistakes and their cost

  1. Advertising the project or opening reservations before any license, which is the closest form of the Article 24 offence.
  2. Receiving a reservation above 5% under a marketing license, or receiving it in an account other than the escrow account.
  3. A feasibility study that assumes the land or finance will be paid from buyers' money without accounting for the 20% cap on non-construction expenses.
  4. Estimating the points on the basis of the foreign parent company's record without confirming whether it counts, then finding that the Saudi entity's points fall short of what the project's size requires.
  5. Delaying local operations (Saudization, social insurance, work regulations) until after the project file is prepared, although they are mandatory qualification criteria.
  6. Contracting an engineering consultant or accountant not approved for the project, or an office without the Balady classification required for a project above SAR 25 million.
  7. Amending the model contract or the executive plans without REGA's approval.
  8. Failing to start works within six months of the license.
  9. A "name for a fee" arrangement with a registered Saudi developer, which leads directly to concealment.

Questions the published official sources do not settle

  • The fee: the Law provides that REGA may charge a fee (Article 27), and the Regulations provide that the Board issues a schedule of fees (Article 48). We did not find the schedule published on the program page, so we state no figures; the reference is what the platform shows at the time of application.
  • The conditions of the immediate path for the off-plan sales license.
  • Whether projects executed outside the Kingdom, or in the name of the parent company or a partner, count towards the Saudi entity's points.

Official sources

Next step

An off-plan file is settled at the start: the developing entity's capacity and points, how the land is secured, the finance structure within the limits of the escrow account, and the boundaries of concealment in any partnership. Investor Journey has a legal team entitled to give legal advice, including on procedural real estate matters such as licenses, contract review and the developer's legal standing. We suggest that you begin with our Legal & Regulatory Advisory service to study your project's structure and the most suitable route for it, or request the Off-Plan Sales License (Wafi) service directly if the entity is registered and the project is ready. If your buyers include non-Saudis, our off-plan developer contract review service allows them to have the contract reviewed before signing, which strengthens their confidence in your project. As for marketing units through a broker, we explain the broker's license in our guide to the FAL real estate brokerage license.

Frequently asked questions

Is entry in the developers' register enough to start selling off-plan?

No. Entry in the developers' register is a condition of carrying on the activity, but each project needs its own license from REGA before units are sold or advertised (Articles 3 and 6 of the Law). Before the project license, a marketing license may be requested under its own conditions.

How much may be received as a reservation before the project is licensed?

During a marketing license, no more than 5% of the unit's value may be received, with disclosure of the project's status and deposit of the amounts in the escrow account (Article 10 of the Regulations). If the marketing license expires without the project license being completed, REGA returns the amounts to their owners.

Can a foreign developer obtain a Wafi license?

The Law requires the developer to be a legal person licensed for the real estate development activity, and states no nationality condition. The foreign investor's route is therefore a Saudi entity registered with MISA with a CR that includes real estate development, followed by qualification in the developers' register and the project license. The most delicate parts of the file are the points tied to a prior delivery record and local requirements such as Saudization.

How long does REGA take to decide?

REGA decides on a marketing license application within 10 working days of the application being complete (Article 8 of the Regulations), and on a project license application within 30 days of the documents being complete; if that period passes without a decision, the application is deemed approved (Article 6 of the Law). This does not include the time needed to prepare the file itself, which is usually the longest part.

What do the engineering consultant and the chartered accountant do?

Both are approved for the project by REGA and certify every disbursement document from the escrow account. The engineering consultant monitors execution and submits progress reports, while the chartered accountant verifies deposits, monitors the cap on non-construction expenses and prepares the financial statements. Both must report the developer's violations within 5 working days.

What is the penalty for selling off-plan without a license?

Imprisonment of no more than five years or a fine of no more than SAR 10 million, or both, and the same applies to collecting money without a license or failing to deposit it in the escrow account (Article 24 of the Law). The Public Prosecution investigates and prosecutes before the competent court.